- Paving on Angus Rd. is happening today (03/21/2024)
- Fiddyment paving is tentatively scheduled for Monday, depending on weather, given Roseville’s policy that paving cannot occur if there’s more than a 30% chance of rain.
- Traffic control is to be dismantled after paving. There will be traffic control for completing minor work but nothing on the scale that we have now.
- Striping/pavement markers is not yet scheduled. There will be traffic control with that.
- This project has obviously taken longer than initially anticipated, but we’re getting close to wrapping it up.